Skip to main content

Requests for Bid - Historic Olivehurst Pipeline Replacement Project Phase 2

OPUD is accepting Bids for OPUD Historic Olivehurst Pipeline Project Phase 2

Notice is hereby given that the Olivehurst Public Utility District will receive sealed bids from prequalified bidders for the construction of the Historic Olivehurst Pipeline Replacement Project at 1970 9th Ave, Olivehurst, CA 95961.  This project consists of constructing approximately 15,000 - 16,000 feet of new PVC C900 water main to replace existing steel mains. The project includes providing approximately 350 new service connections for residential meters. In addition to reconnecting to existing meters, around half of the meters will need to be relocated to make way for new curb, gutter, and sidewalk to be constructed at a later date. As part of the water main installation all associated appurtenances will also be installed, including shut off valves, fire hydrants, blow off and air release valves (where applicable and outlined in the Improvement Plans). 

Note an addendum will be provided next week that will include a bid alternative item for improvements of new PVC C-900 for steel main replacement from Olivehurst Ave past Ardmore on 11th Ave.

The Bid Package may be obtained from Public Works Manager, Swarnjit Boyal via the following methods: Electronic copy by email (provided in hyperlink below an with sboyal@opud.org. For all hard copies, please come into the office located at 1970 9th Ave, Olivehurst, CA and paying via cash or check for a non-refundable amount of $100. Checks will be made out to Olivehurst Public Utility District. 

There is a voluntary Pre-Bid meeting that will start at the District, 1970 9th Ave, Olivehurst, CA starting on Tuesday at 9 AM on February, 25th 2025. Soon after, we will head over to project site/s to go over any additional items identified as relevant via onsite coordination to answer any and all questions.

Note that Road Restoration and trenching requirements fall under Yuba County Jurisdiction.

Note, that is project is funded via the State of California (Department of Water Resources) through the Urban Community Drought Relief Grant. OPUD will pay the awarded bidder per the Prompt Payment Act (Cal. Bus. Prof. Code §7108.5 and Cal. Pub. Contractor Code §§10261.5, 10262, and 10853). OPUD encourages progress payments and are recommended for submittal on a monthly basis. Any applicable federal requirements apply to this project.

Bids are due no later than 2 PM, Thursday, April 3,  2025. 

For any questions please contact Swarnjit Boyal at 530-682-0736 (sboyal@opud.org).

 

Bid Documents (Click Below

OPUD - Historic Pipeline Replacement Project - Phase 2 - Bid Package.pdfOPUD Steel Main Phase 2 Bidders List Dated Feb 25 2025.pdfCounty Fee Estimate - Phase 2.xlsxDrawings - OPUD - Historic Pipeline Replacement Project -Phase 2 - Amendment 1.pdfOPUD Steel Main Phase 2 Bidders List Dated Feb 25 2025.pdfPhase 2 - Addendum 1 - Changelog.pdfPhase 2 - Bidder Questions.pdfSpecifications - Division 1.pdfSpecifications - Division 2.pdfDocument 00 11 16 Notice Inviting Bids.pdf02575 PAVEMENT RESTORATION.pdf02491 LANDSCAPING REPAIRS.pdfCounty Slurry Seal Special Provisions.pdfOPUD02-C01-07_CANAL 4th-C1.pdfDocument 00 41 13 Bid Form.pdfOPUD02-C01-07_CANAL 4th-C2.pdfOPUD02-C01-07_CANAL 4th-C3.pdfOPUD02-C08-10_TULSA_OKMULGEE-C9.pdfOPUD02-C01-07_CANAL 4th-C4.pdfOPUD02-C08-10_TULSA_OKMULGEE-C10.pdfOPUD02-C01-07_CANAL 4th-C6.pdfOPUD02-C01-07_CANAL 4th-C7.pdfOPUD02-C11-14_PACIFIC-C12.pdfOPUD02-C01-07_CANAL 4th-C5.pdfOPUD02-C08-10_TULSA_OKMULGEE-C8.pdfOPUD02-C11-14_PACIFIC-C13.pdfOPUD02-C28-33_ARDMORE_11th-C32.pdfOPUD02-T's and D's-D2.pdfOPUD02-C28-33_ARDMORE_11th-C33.pdfOPUD02-C36-37_8th Ave-C36.pdfSection 01 11 00 Summary of Work.pdfPhase 2 - Addendum 2 - Changelog.pdfPhase 2 - Addendum 2 - Bidder Questions.pdfOPUD - Historic Pipeline Replacement Project -Phase 2 - Addendum 2.pdfPhase 2 - Addendum 3 - Bidder Questions.pdfDocument 00 41 13 Bid Form.pdf

 

Below you find the bid results from todays opening (April 3, 2025) . OPUD intends to go to the board with RCI as the awarded lowest bidder (see  letter below). This letter triggers the five (5) day protest period of which those that bid on the project may submit protests per bid requirements (please follow instructions if you intend to protest). We want to thank everyone for submitting bids and taking time to invest in this project. We look forward to the next one. Have a great rest of your week.

20250403_OPUD_Historic Pipeline Replacement Project - Phase 2_RCI General Engineering_Intent to Award for Construction.pdfOlivehurst Steel Main Phase 2 Bid Opening April 3 2025.pdf

 

Please see the attached protest response letter listed below. Should you have any questions, please reach out to Swarnjit Boyal, Public Works Manager.

Letter Responding to Flowline Protest re Historic Pipeline Replacement Project.pdf20250409_Flowline Contractors Inc_Bid Protest.pdfOPUD Historic Pipe Replacement- Flowline Bid Documents Omissions.pdf

 

Notice of Award (see below)

20250418_Document 00 51 00_Notice of Award_RCI General Engineering.pdf

 

KEEP IN MIND IMPORTANT DATES:

  • February 25, 2025 -  Prebid meeting (voluntary)
  • March 26, 2025 - RFI Questions Due By 2 PM 
  • April 3, 2025 - Bids Due by 2 PM (NO exceptions)